Upgrading Infrastructure: A critical component to Wharton Street Revitalization

Crews continue to make steady progress on the Wharton Street Revitalization project.

Over the past week, work has included:

  • Completion of the storm main installation along Henry Avenue, improving drainage and stormwater management in the area
  • Installation of electrical junction boxes, service conduits and service connections along Wharton Street to support upgraded power and communication infrastructure
  • Installation of shallow utilities along Wharton Street
  • Installation of street light post foundations along Wharton Street

A Summary of Infrastructure Improvements

But what infrastructure upgrades will we see at the end of this project? We thought we’d take a moment to outline how we are making intersections safer, upgrading aging infrastructure (road, storm, water) to be more resilient and to accommodate change, and create opportunities for more biking and walking, economic development, and places to gather. The following table summarizes the expected improvements:

INFRASTRUCTURE UPGRADE

PROJECT LOCATION

CONSTRUCTION PHASE

DESCRIPTION

Multi-use Pathway Addition

Wharton Street

Phase 1 (May – November 2025)

Provide connectivity east and west of the downtown core, outlined in the Transportation Master Plan (2025).

Plaza and sidewalk upgrades

Henry Road, and Memorial Park

Phase 1 (May to November 2025)

Connecting downtown to Memorial Park, creating spaces to gather, celebrate and remember. Provides space for future economic development.

Roadway upgrades

Wharton Street, Victoria Road and Kelly Ave.

Phase 1 & 2 (May – September 2025)

Renewal of aging infrastructure to continue to service existing community.

Stormwater infrastructure upgrades

Wharton Street, Henry Road, and Victoria Road

Phase 1 & 2 (May – September 2025)

Renewal of aging infrastructure to continue to service existing community.

Relocation of overhead power lines

Wharton Street, Victoria Road, Alley way, Rosedale Road, and Armstrong Road.

Phase 1, 2, 3 and 4 (May – November 2025)

Upgrading electrical infrastructure to increase capacity for growth and support redevelopment opportunities.

Intersection safety improvements

Main Street and Victoria Road N

Phase 2 (July – September 2025)

Enhance safety for pedestrians, by slowing traffic at the intersection.

Water infrastructure upgrades

Victoria Road

Phase 2 (July – September 2025)

Renewal of aging infrastructure to continue to service existing community.

Construction Timeline

As always, we appreciate your patience and understanding as construction continues.

For the latest updates, stay tuned to whartonstreet.ca.

If you have any questions or concerns, please email works@summerland.ca or call 250-494-0431.